Progress Report
|
|
|
|
|
|
|
|
|
|
Helmet |
|
|
|
|
|
Start of Project
| Sep | 25 | Request for quotation including part data and mold specifications received. |
| Oct | 20 | Approval to proceed with concept mold design received. |
| Oct | 27 | Mold concept design submitted. |
| Nov | 06 | Quotation submitted. |
| Nov | 13 | Mold concept design approved. Steel and accessories ordered accordingly. |
| Nov | 19 | Verbal approval to proceed with project received. Verbal purchase order received. |
| Dec | 22 | Purchase order and down payment received by mail. |
| Oct | 15 | Revision 1 (2D and 3D) |
| Oct | 23 | Revision 2 (2D and 3D) |
| Dec | 07 | Revision 3 (2D and 3D) |
| Dec | 15 | Revision 4 (2D and 3D) |
| Dec | 23 | Revision 5 (2D and 3D) |
| Nov | 11 | Material, shrinkage and related data specifications received. |
| Oct | 27 | Concept mold design completed. |
| Dec | 07 | Preliminary mold design submitted for review and approval |
| Dec | 15 | Comments to preliminary mold design received. |
|
| Nov | 13 | Materials for mold construction ordered. |
| Dec | 11 | Materials delivered in full. |
|
| Mar | 08 | Scheduled first test of mold. Work proceeding on schedule. |
| Mar | 29 | Forecasted shipment of mold. Mold scheduled to ship via airfreight. |